Green Hill Solar (GHSF) are running a targeted consultation from 13 March to 10 April. See GHSF’s letter announcing the consultation and process. The documentation is available on their website from 13 March.
GHSF will also be delivering a newsletter. Read it here.
The Parish Council will consider the letter and consultation at their meeting on 17 March. See also the Parish Council’s summary page.
Changes Being Consulted on
As part of the design refinement, additional areas of land, predominantly within highways land, have been identified beyond the scheme boundary limits that were presented as part of the statutory consultation process. The proposed changes are transport-related and are for ensuring sufficient land is available to facilitate vehicle access to the sites and the cable route corridor.
The land may be required for traffic management measures during the construction, operational or decommissioning phases.
There are 25 changes in total to the scheme boundary, and they are situated along Broughton Road, Kettering Road, Red House Lane, Moonshine Gap, Highfield Road, Mears Ashby Road, Earls Barton Road, B573, Station Road, A509, Easton Lane, A510 and A428.